Expected Title Timeline – Last Updated: 08.11.2019
Welcome to the Manzeene Village Project Update page. Here you will find some helpful up-to-date information regarding the construction of your stage.
Sewer works are now complete in Stage 4 with drainage work currently underway as is the O’Hallorans Rd road boxing. Sewer and drainage works have been completed in Stage 6, with water well progressed and due for completion over the coming weeks at which time gas installation will follow. Road construction has also commenced where possible.
Stage 7 is nearing completion. Final asphalt is the only remaining stage works to complete. We are awaiting sign-off on the existing road pavement layers from Council before laying asphalt to ensure the stage is well-positioned to achieve Statement of Compliance upon completion of asphalt, we have now commenced working through all Authority testing & auditing processes. The Statement of Compliance is expected in August with lodgement at the Titles Office to follow.
Drainage works have been completed in Stage 8A to service the development of the stage with water construction now underway.
Bulk earthworks are complete in Stage 9A, 9B & 10 with sewer works commenced.
Initial landscape works have commenced for Stage 5 wetland, with the clearing of weeds and debris. Further landscape works are scheduled for the first week of August, with tree planting to start shortly after.
The wetland will be completed and open to the public by the end of October for you and your family to enjoy.
Please find approximate timings in the table below where you will receive further updates as construction commences.